South Dakota Bids > Bid Detail

Watertown WWTF and Collection System Improvements

Agency: Watertown
Level of Government: State & Local
Category:
  • S - Utilities and Training Services
Opps ID: NBD16017169837266263
Posted Date: Nov 18, 2022
Due Date: Dec 16, 2022
Solicitation No: 2317
Source: https://www.watertownsd.us/bid...
Bid Number: 2317
Bid Title: Watertown WWTF and Collection System Improvements
Category: Sewer Department Bids
Status: Open

Description:

REQUEST FOR QUALIFICATIONS/PROPOSALS

WWTF AND COLLECTION SYSTEM IMPROVEMENTS CONSTRUCTION MANAGER AT RISK, PROJECT 2317

CITY OF WATERTOWN, SD

General Notice

City of Watertown (Owner) is requesting Proposals for the following Project:

WWTF AND COLLECTION SYSTEM IMPROVEMENTS CONSTRUCTION MANAGER AT RISK, PROJECT 2317

Proposals will be received via email at the following email address: mlewno@watertownsd.us For security reasons, you must enable JavaScript to view this E-mail address. until Friday, December 16, 2022 at 2:00 p.m. local time.

The purpose of this proposal is to facilitate the selection of a Construction Manager at Risk (“CMAR”) firm to provide preconstruction and construction services for the construction of improvements to the City’s wastewater treatment facility (WWTF) and wastewater collection system.

The proposed project will consist of, but is not limited to, the following: sanitary sewer replacement, sanitary sewer lining, WWTF equipment replacement/addition, new aeration basin, new final clarifier, general WWTF improvements.

Obtaining the Proposal Documents

Information for the Project can be found at the following designated website:

www.watertownsd.us

Proposal Documents may be downloaded from the designated website. The designated website will be updated periodically with information relevant to submitting a Proposal for the Project. All official Proposal Documents will be offered only through the designated website.



The City of Watertown (Owner) has issued this one-step solicitation for the Watertown

WWTF and Collection System Improvements Project (Project) and invites responses to

this request for qualifications/proposals (RFQ/P).

Firms interested in providing construction management at-risk (CMAR) services for the

Project should submit their Proposal according to the requirements set forth in this

RFQ/P, including the format and content guidelines in Section 5. Proposals will be

reviewed, evaluated, and ranked using a qualifications-based/best-value selection

process, as described in Section 6, for award of the CMAR Contract, which is provided

as RFQ/P Attachment C (Draft CMAR Contract).

This project involves improvements to both the City of Watertown wastewater collection

system and the wastewater treatment facility (WWTF).

The City of Watertown wastewater collection system consists of approximately 135

miles of sanitary sewer pipe and 48 City-owned lift stations. The wastewater is

collected and delivered to the WWTF for treatment. Portions of the collection system

are in need of repair.

The City of Watertown WWTF serves a population of 25,000 and treats mainly

municipal wastewater at an average design flow of 4.0 MGD. Treated water is

discharged to the Big Sioux River.

The WWTF was originally constructed in the 1930’s. Major facility expansions occurred

in the 1960’s, 1990’s and 2010’s. A facility plan and condition assessment were

completed in 2021. Many of the improvements for the current project were identified in

this facility plan. Improvements are required to the WWTF due to process reliability,

new discharge permit requirements, and capacity needs related to City growth.

City of Watertown sanitary sewer design standards apply to this project. The Project

will be partially funded by SRF funds and ARPA funds; therefore, SRF and ARFP

requirements apply. Additional information specific to the Project scope, design

standards, and technical requirements are described in more detail in RFQ/P

Attachment D (Project Description and Background Information) and RFQ/P Attachment

E (Facility Plan).

Publication Date/Time:
11/16/2022 4:30 p.m.
Publication Information:
Watertown Public Opinion
Closing Date/Time:
12/16/2022 2:00 p.m.
Submittal Information:
Proposals Submitted to City of Watertown, SD
Addendum Date/Time:
Addendum 1 - 11/18/2022
Contact Person:
Marci Lewno with the City of Watertown via email: mlewno@watertownsd.us
Download Available:
City Web Page
Business Hours:
M-F, 8:00 AM to 5:00 PM
Fax Number:
605-882-5264
Plan Holders List:
If you would like to be placed on a plan holders list please email Marci at mlewno@watertownsd.us
Miscellaneous:
Confidential individual meetings between each Proposer and the City will be held prior
to the submittal of the Proposal. The meetings will allow each Proposer to ask detailed
Project questions. These meetings are optional. Owner will provide each Proposer
access to the WWTF after the meeting to tour the Project site in order to familiarize
themselves with site conditions and constraints.
Meetings may be scheduled for one of the following dates: December 1, 2, 5, or 6,
2022. To schedule a meeting, the Proposer shall contact Marci Lewno with the City of
Watertown via email: mlewno@watertownsd.us by November 30, 2022.
Related Documents:

TRY FOR FREE

Not a USAOPPS Member Yet?

Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.