SD FLAP CS23A(1) - DELTA-01 ACCESS ROAD
Agency: | TRANSPORTATION, DEPARTMENT OF |
---|---|
Level of Government: | Federal |
Category: |
|
Opps ID: | NBD00159732576527870 |
Posted Date: | Apr 20, 2023 |
Due Date: | May 5, 2023 |
Solicitation No: | 6982AF23B000020 |
Source: | https://sam.gov/opp/4b1a63958c... |
Procurement Technical Assistance Centers (PTACs) are an official government contracting resource for small businesses. Find your local PTAC (opens in new window) for free government expertise related to contract opportunities.
- Contract Opportunity Type: Presolicitation (Original)
- All Dates/Times are: (UTC-06:00) MOUNTAIN STANDARD TIME, DENVER, USA
- Original Published Date: Apr 20, 2023 03:11 pm MDT
- Original Response Date: May 05, 2023 02:00 pm MDT
- Inactive Policy: 15 days after response date
- Original Inactive Date:
-
Initiative:
- None
- Original Set Aside:
- Product Service Code: Y1LB - CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
-
NAICS Code:
- 237310 - Highway, Street, and Bridge Construction
-
Place of Performance:
Wall , SDUSA
THIS IS NOT A REQUEST FOR BID
PLANS AND SPECIFICATIONS ARE NOT AVAILABLE
THIS IS FULL AND OPEN COMPETITION
PROJECT NUMBER: SD FLAP CS23A(1)
PROJECT NAME: DELTA-01 ACCESS ROAD
PROJECT DESCRIPTION: The Delta 01 site is located 0.6 miles north on CS-23A from exit 127 off of I-90. Delta 01 is in Jackson County, South Dakota, about 17 miles from the Town of Wall. The access road to the Delta 01 missile site is CS-23A and owned and operated by Jackson County. The project will improve access to the Delta 01 Launch Control Facility. The existing gravel roadway will be widened to match the state-owned portion of the road and paved to provide a durable driving surface. Several existing culvert issues along the route will be addressed to reduce future maintenance costs for the County.
SCOPE OF THE WORK: Proposed improvements to CS-23A include paving 0.51 miles of the county road and widening the existing travel way 17 feet wide, to 24 feet wide, providing two travel lanes 11 feet wide with new paved shoulders one foot wide. Improvements also will include installing Manual on Uniform Traffic Control Devices (MUTCD) compliant signing and striping. The proposed improvements will improve public access to the Delta 01 Launch Control Facility.
Shoulder erosion was observed along the southeastern edge of the project. Embankment will be constructed to fill the erosion area and graded to provide positive drainage to the north. A culvert failed during spring 2019, necessitating an emergency backfill of the road by Jackson County. Three new larger culverts will be placed to provide improved drainage.
The project’s assets are owned by Jackson County. The current roadway has several culverts full of sediment and have overtopped causing damage to the roadway. Placing new, appropriately sized culverts will decrease future maintenance issues. Placing asphalt concrete pavement will decrease the annual maintenance necessary to grade and re-gravel this section of CS-23A.
Recently, the National Park Service (NPS) built a paved parking lot and comfort station on the east side of CS-23A, across from the Delta 01 site.
PRINCIPAL WORK ITEMS:
- 1,500 CUYD of Embankment Construction
- 3,150 Tons of Aggregate Base
- 2,000 Tons of Asphalt Concrete Pavement, Type 1
- 1,000 hours of Temporary Traffic Control, Flagger
- 0.6 miles of Ditch Reconditioning
- 4 Concrete, Headwall for 36-Inch Pipe Culvert
The estimated price range of the project work is between $700,000 and $2,000,000.
- 12300 W. DAKOTA AVE
- LAKEWOOD , CO 80228
- USA
- KELLY PALMER
- CFLAcquisitions@dot.gov
- Phone Number 7209633500
- Apr 20, 2023 03:11 pm MDTPresolicitation (Original)
- Mar 10, 2023 09:59 pm MST Sources Sought (Inactive)
TRY FOR FREE
Not a USAOPPS Member Yet?
Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.